LearnCompareSolutionsPricingArchitectureFAQAboutSign in

Monte Carlo schedule risk analysis (and what a P80 date is)

Explore possible finish dates, see what drives them, and make the model's assumptions visible.

Last updated:

Monte Carlo schedule risk analysis repeatedly calculates a schedule with sampled task durations and risk events. The resulting finish dates form a distribution. This lets a program team assess a proposed deadline rather than treating one deterministic date as certain.

The output is conditional evidence. More iterations reduce sampling noise, but they cannot repair missing dependencies, unsupported duration estimates, or omitted risks. Review the schedule before interpreting its percentiles.

Start with a credible dependency model

Define the work, owners, relationships, lags, calendar assumptions, and endpoint. Check open ends, constraints, and resource conflicts. A deterministic schedule is a useful baseline. Its single finish date does not specify the probability of meeting it.

At a merge point, the successor must wait for the required predecessors. Sampling their durations can reveal a different controlling path in different runs. The simulated median can be later than the deterministic date, but that is not a universal rule.

Estimate uncertainty and discrete risks

Three-point duration estimates describe an optimistic bound, a most-likely value, and a pessimistic bound under a stated model. Beta-PERT is one possible distribution. Other analysis tools might support different shapes. Do not treat bounded inputs as percentile estimates without an appropriate fitting method.

A discrete risk has a probability and an impact on specified work. Avoid counting the same delay both in the base duration range and again as a separate event. Document common causes before choosing correlation assumptions.

Read P50, P80, and P90 correctly

P50 is the median modeled finish. P80 is reached in 80% of simulated outcomes, leaving 20% later. P90 leaves 10% later. Choose the confidence target with the decision owner based on the consequences of delay.

A percentile is not a regulatory approval date or a delivery guarantee. State the model revision, exclusions, and endpoint with the forecast. Calculate reserve relative to a named baseline, which need not be P50.

Use criticality and sensitivity together

Criticality measures how often a task is on the controlling path in the simulation. Sensitivity measures association between an input and the finish. A frequently critical task can have little duration variability. Correlated inputs can complicate interpretation.

Use these outputs to select questions and candidate responses. Rerun a mitigation scenario to estimate its effect. A high correlation alone does not prove causation or tell you which response is cheapest.

What CritPath computes

CritPath samples Beta-PERT durations and task-linked risk impacts. It calculates finish-date percentiles, criticality from total float across forward and backward passes, and Spearman duration-sensitivity rankings. Optional correlation uses a shared project-level setting. It is not an arbitrary pairwise correlation matrix.

CritPath's current simulation models finish-to-start relationships with lag and reports the modeled project endpoint. Its deterministic CPM engine supports additional dependency types. Review models with start-to-start, finish-to-finish, or start-to-finish links before using their simulated forecasts for a commitment.

When a target confidence level and simulation result are available, CritPath sizes the project buffer from the selected percentile minus the deterministic CPM endpoint, floored at zero. Otherwise it uses a sum-of-squared-safety heuristic. Feeding buffers use a heuristic that can be scaled with the project buffer. They are not independent percentile forecasts.

Iteration counts are configurable. Check result stability for the decision at hand. Runtime depends on model size, settings, and infrastructure.

Pro is $25 per user per month at the standard price. The first 200 customers receive founder pricing of $10 per user per month, with personal installation, setup, and guidance from the founder and developer. AI is billed separately per completed job at estimated token cost plus a platform margin. Failed runs are not billed.

Frequently asked questions

What is a P80 date?

It is a date reached in 80% of the simulated outcomes for the modeled endpoint. The remaining 20% finish later, and the result depends on the assumptions.

Must the deterministic date be earlier than P50?

No. Its position depends on the duration inputs, risk model, constraints, and network. It has no intrinsic confidence level.

How many iterations are enough?

Compare repeated runs or increased iteration counts until the percentiles and rankings are stable enough for the decision. More runs do not correct poor inputs.

Can I use the forecast for a named milestone?

Confirm that the modeled endpoint represents that milestone and includes the work needed to reach it. CritPath's current schedule simulation reports the project endpoint.

Sources and methodology

These references explain the methods and program context. They do not endorse or certify CritPath AI.

  • Schedule Assessment Guide

    U.S. Government Accountability Office

    Guidance on schedule logic, risk analysis, contingency, and maintaining a reliable schedule. Not an endorsement of CritPath.

  • Schedule Management Handbook

    NASA

    Methodology for schedule assessment, uncertainty, risk analysis, and interpreting results.

Related

Bring the assumptions with the date

Run a schedule simulation and examine the modeled finish distribution. Review its inputs and dependency assumptions before sharing a confidence forecast.

Get started