LearnCompareSolutionsPricingArchitectureFAQAboutSign in

Learn schedule-risk management

Plain-English guides to the methods behind CritPath AI — critical chain, Monte Carlo, critical path, Theory of Constraints, and AACE Level 4 risk-driven scheduling.

What is Critical Chain Project Management (CCPM)?

A plain-English guide to Critical Chain Project Management (CCPM): how it differs from the critical path, how project and feeding buffers work, and how to manage with a fever chart.

What is schedule risk analysis (SRA)?

What quantitative schedule risk analysis requires, how to read its forecasts, and how R&D teams evaluate model quality, contingency, and software fit.

Monte Carlo schedule risk analysis (and what a P80 date is)

Learn how Monte Carlo schedule analysis turns duration ranges and risk events into P50, P80, and P90 forecasts, criticality, and sensitivity results.

What is the Critical Path Method (CPM)?

Understand the critical path method: early and late dates, total and free float, near-critical paths, dependency types, and schedule assumptions.

Theory of Constraints in project management

How the Theory of Constraints and Drum-Buffer-Rope work in project management: the five focusing steps, the drum constraint, subordination, buffers, and the link to CCPM.

AACE 132R-23 Level 4 and schedule risk maturity

Understand AACE RP 132R-23, its Level 0-5 maturity model, integrated cost-schedule risk at Level 4, and the evidence to review before claiming alignment.

WSJF and cost of delay explained

Learn weighted shortest job first and cost of delay with a worked example. Check economic assumptions, dependencies, and resource constraints before sequencing work.

Decision gates in project management

Define decision gates, evidence, owners, and Go/No-Go/Pivot/Defer outcomes. Learn how to connect a stage-gate review to an R&D schedule and its dependencies.

Fever charts and buffer management in Critical Chain

Understand a CCPM fever chart, buffer consumption, and progress. Learn why alert colors are management thresholds, not forecast probabilities.

Earned value management explained

Learn earned value management formulas for PV, EV, AC, SPI, CPI, and EAC. Work through an example and distinguish progress metrics from finish-date forecasts.

What is a three-point estimate?

A plain-English guide to three-point estimates: optimistic, most likely, and pessimistic values, the PERT weighted mean (O+4M+P)/6, the PERT-Beta distribution, and why single-point dates mislead.

Tornado charts and schedule sensitivity analysis

Read schedule sensitivity and tornado charts correctly: distinguish correlation, criticality, and mitigation impact before changing an R&D plan.

Criticality index in Monte Carlo schedule analysis

What the criticality index is, how it differs from the deterministic critical path, why near-critical tasks matter, and how CritPath AI reports it from a Monte Carlo run.

Drum-Buffer-Rope (DBR) explained

Understand Drum-Buffer-Rope: constraint pacing, protective buffers, controlled work release, and the relationship to critical chain project management.

Schedule contingency: what it is and how to calculate it

Calculate schedule contingency from a chosen baseline and target confidence date. Understand P80 minus P50, deterministic baselines, and buffer limits.