What is schedule risk analysis (SRA)?
Connect the dependency plan, uncertainty, and risk register to a forecast you can examine.
Last updated:
Schedule risk analysis examines how uncertainty affects a project's completion. Quantitative schedule risk analysis, or QSRA, uses a model to estimate finish-date distributions and identify important drivers. It complements the deterministic plan used to coordinate work.
For a biotech, hardware, or federal research program, ask what can move the milestone, by how much, and under which assumptions. Use the forecast to support that decision without presenting modeled confidence as a promise.
Assess the schedule before simulating it
Check that the work needed for the endpoint is present and connected. Review durations, relationship types, calendars, constraints, resource availability, and actual progress. Missing work or an incorrect dependency can outweigh the benefit of thousands of simulation iterations.
A deterministic plan can be optimistic or conservative. Its finish date does not carry an implied P50 or other percentile. Simulation adds a probability model rather than proving that every single-date plan is wrong.
Document the uncertain inputs
Use evidence from task owners, suppliers, comparable work, and organizational history to estimate duration ranges. Give discrete risks an owner, occurrence probability, impact, and affected work. Record what the model excludes.
Consider common causes and correlation, and avoid double-counting risks already included in duration estimates. Review uncertain technical decisions separately from routine execution variability.
Interpret the outputs
P50, P80, and P90 are percentiles of simulated finishes. Criticality identifies tasks that frequently control completion. Sensitivity ranks statistical associations with the finish. None of these outputs alone selects a mitigation or establishes its cost effectiveness.
Contingency is measured between a defined baseline and a target date. For example, P80 minus P50 is appropriate only when P50 is the chosen baseline. Keep the forecast, baseline, calendar, and assumptions together in program reports.
Evaluate a change before accepting it
For an IND-readiness review, test a CMC delay and examine the downstream evidence needed for filing. For a hardware build, test a supplier delay before the integration slot. For a research program, test a partner handoff before the sponsor review.
Compare the changed scenario with the original model and record the decision. These are evaluation workflows, not claims that software can remove the underlying technical or delivery risk.
Methodology and compliance boundaries
GAO and NASA publish guidance for reliable schedules and risk analysis. AACE RP 132R-23 is a schedule-risk maturity model. A software feature list or audit trail does not certify an organization's maturity or establish regulatory compliance.
Check the actual project requirements, analytical method, validation evidence, security controls, and review process. Procurement and assurance decisions require evidence beyond a marketing page.
How CritPath supports the workflow
CritPath combines deterministic CPM, Beta-PERT simulation, task-linked risk events, criticality and sensitivity outputs, buffers, decision gates, and schedule-aware AI assistance. Review AI-generated estimates and recommendations before relying on them.
CritPath's current simulation models finish-to-start relationships with lag and reports the modeled project endpoint. Its deterministic CPM engine supports additional dependency types. Review models with start-to-start, finish-to-finish, or start-to-finish links before using their simulated forecasts for a commitment.
When a target confidence level and simulation result are available, CritPath sizes the project buffer from the selected percentile minus the deterministic CPM endpoint, floored at zero. Otherwise it uses a sum-of-squared-safety heuristic. Feeding buffers use a heuristic that can be scaled with the project buffer. They are not independent percentile forecasts.
Pro is $25 per user per month at the standard price. The first 200 customers receive founder pricing of $10 per user per month, with personal installation, setup, and guidance from the founder and developer. AI is billed separately per completed job at estimated token cost plus a platform margin. Failed runs are not billed.
Frequently asked questions
How does QSRA differ from a schedule review?
A schedule review checks the model's quality and assumptions. QSRA adds quantified uncertainty and risk analysis. A credible quantitative run still needs a sound underlying schedule.
What does a P80 forecast mean?
The modeled endpoint finishes by that date in 80% of simulated outcomes. It is conditional on the model and is not a delivery guarantee.
Does software establish AACE or regulatory compliance?
No. The organization must assess its method, controls, evidence, and applicable requirements. A tool can support the work without certifying the program.
What does a useful evaluation demonstrate?
Import representative work, check its logic, change a risk or duration, rerun the analysis, and explain the resulting dates, assumptions, and limitations.
Sources and methodology
These references explain the methods and program context. They do not endorse or certify CritPath AI.
- Schedule Assessment Guide
U.S. Government Accountability Office
Guidance on schedule logic, risk analysis, contingency, and maintaining a reliable schedule. Not an endorsement of CritPath.
- Schedule Management Handbook
NASA
Methodology for schedule assessment, uncertainty, risk analysis, and interpreting results.
Related
Put uncertainty into the plan
Model duration ranges and task-linked risks, then review completion percentiles, criticality, and sensitivity for your project endpoint.
Get started