What is the Critical Path Method (CPM)?
Use early and late dates to find controlling work, then examine the uncertainty behind the plan.
Last updated:
The critical path method (CPM) calculates a project's earliest finish from task durations and dependency logic. In a finish-to-start model without additional constraints, the longest chain of dependent tasks controls that finish. Calendars, other relationship types, and imposed constraints require additional interpretation.
CPM identifies controlling work and available float under the stated assumptions. A Gantt chart displays the plan. Displaying one does not by itself mean the software calculates CPM.
The schedule network: tasks, dependencies, and duration
CPM models a project as a directed network of tasks (activities) connected by dependencies. Each task has a duration, and each dependency says that one task constrains when another can start or finish. From this network and the task durations, CPM computes the start and finish dates for every task and identifies the critical path.
Basic CPM evaluates dependency logic without resolving resource contention. Two tasks can be ready at the same time even if both need the same engineer. Review resource availability separately when deciding whether the calculated sequence is feasible.
The forward pass: earliest start and finish
The forward pass computes early dates through the network. With finish-to-start relationships and zero lag, a task starts no earlier than the latest predecessor finish. Add its duration to get its early finish. Other relationship types, lags, and constraints change these calculations. The latest task finish defines the modeled project endpoint.
These are the earliest dates permitted by the modeled logic and durations. They are not an optimistic percentile or a guarantee that resources are available to perform the work.
The backward pass: latest start and finish
The backward pass works from the project finish to calculate late dates. With finish-to-start relationships and zero lag, a task's late finish is the earliest late start among its successors. Subtract its duration to get its late start. Other relationship types, lags, and constraints require corresponding adjustments.
The two passes produce early start (ES), early finish (EF), late start (LS), and late finish (LF). Comparing the early and late dates shows the available float under the model.
Total float, free float, and the critical path
Total float is the time a task can move without delaying the modeled project finish: late start minus early start, or late finish minus early finish. Free float measures the room before an immediate successor's early date is affected. A task can have total float but zero free float.
In a network scheduled to its earliest finish without imposed deadlines, zero-total-float activities identify controlling work. There can be multiple critical paths. Date constraints and calendars can complicate float, so inspect the logic before interpreting a delay.
- Total float: slack relative to the modeled project finish.
- Free float: slack before an immediate successor's early date is affected.
- Critical path: a controlling path through the modeled schedule.
Near-critical paths: the trap of looking only at zero float
A near-critical path has little float in the baseline. A delay can consume that margin and make it controlling. For example, a feeder with one working day of float starts affecting the downstream plan after that margin is exhausted, assuming the other inputs stay fixed.
Review low-float work alongside the deterministic critical path. Simulation can show how often different activities become critical as durations and risk events vary.
The four dependency types and lag
Four relationship types connect a predecessor and successor. Finish-to-start (FS) constrains the successor's start relative to the predecessor's finish. Start-to-start (SS) connects starts, finish-to-finish (FF) connects finishes, and start-to-finish (SF) constrains the successor's finish relative to the predecessor's start.
Lag offsets the relationship. An FS relationship with five working days of lag means the successor cannot start before five working days after its predecessor finishes. Other constraints can make it start later. Negative lag permits overlap. Keep review, shipping, or other work visible as activities when that better represents responsibility and uncertainty.
- Finish-to-start: successor start depends on predecessor finish.
- Start-to-start: successor start depends on predecessor start.
- Finish-to-finish: successor finish depends on predecessor finish.
- Start-to-finish: successor finish depends on predecessor start.
- Lag or lead: a positive or negative offset to the relationship.
Why CPM alone does not quantify uncertainty
CPM provides a dependency-based planning baseline from fixed inputs. It does not describe the range of possible task durations or the chance of a risk event. Add an uncertainty model when the decision requires a probabilistic forecast.
A single-point finish has no implied confidence level. It can be optimistic or conservative depending on the inputs. A simulation can show how duration uncertainty and changing controlling paths affect the modeled completion distribution.
How CritPath AI builds on CPM
CritPath provides deterministic CPM with four dependency types, lag, float, and near-critical analysis. It also provides Beta-PERT simulation, risk events, criticality, sensitivity, buffers, and decision gates. The simulation uses a finish-to-start plus lag simplification, so validate other relationship types before using its forecast. Schedule-aware AI assistance can help explain the recorded plan, with important conclusions checked against the underlying evidence.
Pro is $25 per user per month at the standard price. The first 200 customers receive founder pricing of $10 per user per month, with personal installation, setup, and guidance from the founder and developer. AI is billed separately per completed job at estimated token cost plus a platform margin. Failed runs are not billed.
Frequently asked questions
What is the critical path in CPM?
A critical path controls the modeled project finish. In a finish-to-start network without imposed deadlines, it is a longest chain of dependent tasks with zero total float. Interpret delays using the actual relationships, calendars, and constraints.
What is the difference between total float and free float?
Total float measures room relative to the modeled project finish. Free float measures room before an immediate successor's early date is affected. A task can have total float but zero free float.
What are the four dependency types in CPM?
Finish-to-start (FS), start-to-start (SS), finish-to-finish (FF), and start-to-finish (SF). Each relationship can include a lag or lead. Review how the selected scheduling engine handles those relationships.
Why isn't the Critical Path Method enough on its own?
CPM calculates a finish from fixed inputs. It does not assign that date a probability. Use an uncertainty model and simulation when you need percentile forecasts.
Does CritPath AI include a full CPM engine?
CritPath provides deterministic CPM with four dependency types, lag, float, and near-critical analysis, alongside simulation and buffer tools. The current Monte Carlo calculation uses finish-to-start relationships with lag, so review other relationship types before relying on a simulated forecast.
Sources and methodology
These references explain the methods and program context. They do not endorse or certify CritPath AI.
- Schedule Assessment Guide
U.S. Government Accountability Office
Guidance on schedule logic, risk analysis, contingency, and maintaining a reliable schedule. Not an endorsement of CritPath.
- Schedule Management Handbook
NASA
Methodology for schedule assessment, uncertainty, risk analysis, and interpreting results.
Related
Understand what controls completion
Calculate early and late dates, float, and the deterministic critical path. Review uncertainty separately with the supported simulation model.
Get started