LearnCompareSolutionsPricingArchitectureFAQAboutSign in

Criticality index in Monte Carlo schedule analysis

See how often a task controls the modeled finish, then examine the size and source of its uncertainty.

Last updated:

The criticality index is the fraction of simulation iterations in which a task is on the critical path. If it is critical in 8,200 of 10,000 runs, its index is 82%. This is a property of the model and sampled scenarios, not a probability that the task itself will be late.

A deterministic network can have multiple critical paths. As durations and modeled risks vary, their controlling role can change. Criticality helps reveal that change, including work with positive float in the baseline.

How the index is calculated

For each iteration, sample durations and risk impacts, calculate early and late times, and identify tasks with effectively zero total float. Count the critical iterations for each task and divide by the number of runs.

For example, a task critical in 600 of 1,000 runs has a 60% index. That does not mean it delays the program in 60% of real projects or causes 60% of the modeled variance.

Read frequency separately from impact

A task can be critical in every run but have a fixed duration. Its criticality is high even though its own duration uncertainty contributes little or no variation. Another task can become critical infrequently but create a large delay when a risk occurs.

Compare criticality with sensitivity, risk impact, available responses, and response cost. There is no universal index threshold that makes every task above it a priority.

Distinguish near-critical float from simulated criticality

Near-critical commonly describes small float in a particular deterministic schedule. Criticality describes frequency across simulations. They are related concepts, but a high simulated index does not imply that a task must have positive float in the baseline.

Review both views when a supplier, laboratory, or shared specialist can shift the controlling path. Investigate the mechanism before selecting a mitigation.

How CritPath reports criticality

CritPath calculates early and late dates in each simulation iteration and counts near-zero total float. This includes upstream controlling tasks, not only tasks that finish at the project endpoint.

CritPath's current simulation models finish-to-start relationships with lag and reports the modeled project endpoint. Its deterministic CPM engine supports additional dependency types. Review models with start-to-start, finish-to-finish, or start-to-finish links before using their simulated forecasts for a commitment.

The same analysis provides Spearman duration sensitivity and finish-date percentiles. Check stability across repeated runs or increased iteration counts before making decisions based on small differences.

Pro is $25 per user per month at the standard price. The first 200 customers receive founder pricing of $10 per user per month, with personal installation, setup, and guidance from the founder and developer. AI is billed separately per completed job at estimated token cost plus a platform margin. Failed runs are not billed.

Frequently asked questions

Does 100% criticality mean a task is the biggest risk?

No. It means the task was critical in every modeled run. Its uncertainty and possible delay impact might still be small.

Can more than one task have 100% criticality?

Yes. Several tasks on a common controlling chain can all be critical in every run. Indices do not sum to 100%.

Is criticality the probability of late delivery?

No. It measures critical-path frequency. A deadline probability is calculated from the distribution of completion dates.

How do I choose a review threshold?

Choose a review threshold suited to the model and decision. Compare impact and response options as well as criticality. There is no universal cutoff.

Sources and methodology

These references explain the methods and program context. They do not endorse or certify CritPath AI.

  • Schedule Assessment Guide

    U.S. Government Accountability Office

    Guidance on schedule logic, risk analysis, contingency, and maintaining a reliable schedule. Not an endorsement of CritPath.

  • Schedule Management Handbook

    NASA

    Methodology for schedule assessment, uncertainty, risk analysis, and interpreting results.

Related

Find work that becomes critical

Review how often tasks control the modeled finish across simulation runs. Compare frequency with sensitivity and the practical options for response.

Get started