What is a three-point estimate?
Describe the range, document what the bounds mean, and keep the mean distinct from the most-likely value.
Last updated:
A three-point estimate describes a task with optimistic, most-likely, and pessimistic durations. It gives a probability model more information than one point estimate, provided the estimator and the tool agree on what the three inputs mean.
For a bounded Beta-PERT model, the optimistic and pessimistic inputs are the modeled lower and upper bounds. They are not automatically P10 and P90. If your estimates are percentiles, fit a suitable distribution rather than entering them as bounds without adjustment.
Define the inputs consistently
Use the same duration units, work scope, resource assumptions, and calendar for all three values. The most-likely value is the mode. It can differ from both the mean and median.
Document the basis of the range: comparable completed work, supplier evidence, expert estimates, or organizational history. Identify whether a discrete risk is already included so it is not counted again in the risk register.
Calculate the PERT weighted mean
With standard Beta-PERT weighting, the mean is (O + 4M + P) / 6. For O = 7, M = 10, and P = 20 working days, the result is 67/6, or about 11.17 days. This is the mean of the assumed task distribution, not the project P50.
The familiar (P − O) / 6 standard-deviation rule is an approximation. It is not generally the exact standard deviation of a fitted Beta-PERT distribution. Use the distribution's parameters when an exact variance is needed.
Use the distribution in a network
Simulation samples each task distribution and calculates the schedule under that draw. Parallel paths, relationships, risks, and correlation affect the resulting project distribution. Summing individual task modes or medians does not generally produce the project median.
A symmetric or skewed Beta-PERT shape depends on the three inputs. A bounded model cannot generate outcomes outside its bounds unless another modeled mechanism, such as a discrete risk impact, extends them.
How CritPath uses the estimates
CritPath uses optimistic, most-likely, and pessimistic durations to sample Beta-PERT task distributions. Optional project-level correlation and task-linked risks can change the finish-date distribution. Review inputs suggested by AI against evidence before accepting them.
CritPath's current simulation models finish-to-start relationships with lag and reports the modeled project endpoint. Its deterministic CPM engine supports additional dependency types. Review models with start-to-start, finish-to-finish, or start-to-finish links before using their simulated forecasts for a commitment.
Check sample outputs against a small known schedule before using a large import. Revise the ranges as work progresses and preserve the assumptions used for each decision.
Pro is $25 per user per month at the standard price. The first 200 customers receive founder pricing of $10 per user per month, with personal installation, setup, and guidance from the founder and developer. AI is billed separately per completed job at estimated token cost plus a platform margin. Failed runs are not billed.
Frequently asked questions
Are optimistic and pessimistic values P10 and P90?
Not in a bounded Beta-PERT input model. They are modeled bounds. Percentile estimates require an appropriate fitting method.
Is the most-likely duration the mean?
No. It is the mode. For a skewed distribution, mode, mean, and median can differ.
Does the PERT mean equal the project P50?
No. It is an expected duration for one assumed task distribution. The project percentile depends on the full network and risk model.
Is (P − O) / 6 the exact standard deviation?
No. It is a traditional approximation. The fitted Beta distribution has its own variance formula.
Sources and methodology
These references explain the methods and program context. They do not endorse or certify CritPath AI.
- Schedule Assessment Guide
U.S. Government Accountability Office
Guidance on schedule logic, risk analysis, contingency, and maintaining a reliable schedule. Not an endorsement of CritPath.
- Schedule Management Handbook
NASA
Methodology for schedule assessment, uncertainty, risk analysis, and interpreting results.
Related
Start with a range you can explain
Enter optimistic, most-likely, and pessimistic duration bounds. Simulate the dependency network and review what those assumptions mean for completion.
Get started