LearnCompareSolutionsPricingArchitectureFAQAboutSign in

Earned value management explained

Measure completed work against its budget, then check the assumptions behind your forecast.

Last updated:

Earned value management (EVM) compares planned work, completed work, and actual expenditure using a common budget basis. It helps you investigate whether the program is delivering the expected scope for the money spent.

An EVM report needs a defined baseline, reliable progress measurement, and costs for the same reporting period. A precise ratio cannot repair inconsistent inputs. Use the result to investigate performance and update your forecast, rather than treating it as a promise about the finish date.

The quantities behind an EVM report

The National Science Foundation's EVM Gold Card defines the principal measures and formulas. Use the same scope and status date for each quantity.

  • Budget at completion (BAC): the budget for the planned scope.
  • Planned value (PV): the budgeted value of work scheduled by the status date.
  • Earned value (EV): the budgeted value of work completed by that date.
  • Actual cost (AC): expenditure for the work performed.

Calculate variances and performance indices

Schedule variance is EV minus PV. Cost variance is EV minus AC. A negative value means earned progress is below the corresponding plan or expenditure. Both variances use budget units, not elapsed days.

The schedule performance index (SPI) is EV divided by PV. The cost performance index (CPI) is EV divided by AC. A value below 1 indicates unfavorable performance against that comparison. A zero denominator makes the ratio undefined.

Consider an illustrative program with BAC of $100,000, PV of $50,000, EV of $40,000, and AC of $48,000. It has earned $10,000 less work than planned and spent $8,000 more than the budgeted value delivered. SPI is 0.80 and CPI is about 0.83. Neither ratio states the number of days the program is late.

Choose an estimate-at-completion assumption

Estimate at completion (EAC) forecasts total cost. One formula is BAC divided by CPI, assuming the observed cost efficiency continues. Estimate to complete (ETC) is EAC minus AC. Variance at completion (VAC) is BAC minus EAC.

For the illustrative program, continuing the same efficiency gives an EAC of $120,000 and an ETC of $72,000. That is a scenario, not a statistical confidence interval. A one-time startup expense or a revised technical approach can make that extrapolation unsuitable.

DOE guidance treats formula-based estimates as analytical aids rather than replacements for a maintained management forecast. Review remaining commitments, changed rates, and known risks when estimating the work left to complete.

Read schedule performance alongside the dependency network

Two programs can have the same SPI and different finish risks. In one, the missing progress belongs to work with float. In another, it belongs to a test that blocks every downstream activity. Inspect the dependency network before deciding what to expedite.

A basic SPI calculation also returns to 1 when all planned work is earned, even if completion was late. Keep actual milestone dates and the schedule forecast alongside it. Monte Carlo analysis can add a distribution of possible dates when its uncertainty assumptions represent the remaining work.

EVM can be part of a broader risk-informed management process. The NSF guidance includes risk-adjusted cost estimates. Basic ratios do not express probabilities, but EVM can still contribute to risk analysis.

What CritPath AI's EVM report calculates

CritPath AI calculates planned and actual labor costs from task assignments and resource rates. It earns value from each task's reported percentage complete and planned cost, then reports cost performance and EAC. The result depends on the completeness of those entries.

Its planned-value calculation is simplified: total planned cost multiplied by the elapsed fraction between the project's start and target dates. Without those dates, PV, SV, and SPI are unavailable. This is not a detailed time-phased baseline for each work package, so assess whether it suits your reporting requirements.

Expanded AI employee workflows are scheduled to launch November 25, 2026, subject to workspace configuration. Review generated explanations against the report inputs. AI cannot establish that an accounting record or progress estimate is correct.

Evaluate the report with your own data

Reconcile a small sample of task budgets, progress, and actual costs before extending the report to a program. Keep an agreed status date and document any costs excluded from the calculation.

Pro's standard price is $25 per user per month. The first 200 customers are offered $10 per user per month with personal setup guidance from the founder and developer. AI usage is separate, per completed job at estimated token cost plus a platform margin. Failed jobs are not billed.

Frequently asked questions

Does SPI measure the number of days a project is late?

No. SPI compares earned value with planned value in budget units. Use milestone dates, dependency analysis, and schedule forecasts to assess calendar impact.

Does CritPath AI provide EVM reports?

Yes. Its labor-cost report calculates earned value and cost performance. Schedule indices require project start and target dates and use a simplified elapsed-time planned value. Confirm that this approach meets your reporting needs.

Sources and methodology

These references explain the methods and program context. They do not endorse or certify CritPath AI.

Related

Review progress and forecast together

Compare cost and progress metrics with schedule-risk results. Keep the earned-value calculation assumptions and simulated completion dates distinct.

Get started